"Drop-dead." That is how Aspen's chief building official, Bonnie Muhigirwa, described the Dec. 31, 2026 expiration of the Aspen Club's latest permit extension, according to Aspen Journalism's October report, which also ran in the Aspen Daily News. The new contractor's schedule puts overall completion around January 2031. For anyone weighing a purchase in the East End, the closer date matters more.
The Condition the City Set in April
In mid-April, Muhigirwa approved another extension on the project's building permits. It came with conditions that work differently from any of the earlier ones. Aspen Journalism reported that the extension holds only if "substantial work continues on the townhome buildings," including reroofing, framing and flashing, and that the clubhouse permit has its own trigger.
"If the work on the club building permit has not recommenced by December 31, 2026, the permit will become invalid."
The same correspondence, as quoted by Aspen Journalism, closed the usual escape route. Asking to amend land use approvals or filing more change orders "will not constitute good cause for justifying additional extensions," and the city said further extension requests are unlikely to be granted. In September, Muhigirwa told the outlet: "This needs to be a real return to work on the site."
Under the old approach, a little work every few months kept the permits alive. Now the clubhouse has to be under real construction by a fixed date, and the site changed this fall. A site office, a crane, excavators and a dozen or so workers in hard hats appeared after years of very little happening. Muhigirwa confirmed concrete-slab inspections on the club building in the weeks before the October report and said she believes the Dec. 31 deadline can be met.
Why a Little Work Used to Be Enough
The deadline matters because of how the previous ten years went. The Aspen Club closed for redevelopment in 2016. Financing fell through, contractors walked off the job in 2017 with the townhomes 60% to 80% complete, and the property sold at a foreclosure auction in early 2021 for $52.6 million. That summer, the new ownership group talked about reopening by winter 2023-24.
City review of the redesigns took most of the time that followed. The project carries five permits: one for the clubhouse, one for the workforce housing, and one for each of three townhome clusters. The clubhouse change order went through five rounds of review between its February 2023 submission and its issuance on April 1, 2026, which is more than three years. The site shut down for more than half of 2024.
Through all of that, the city treated progress on any part of the project as enough to keep every permit alive. Work on the townhomes kept the clubhouse permit active. Muhigirwa called expiring a permit "a very punitive and final act" that can affect a project's vested rights and sometimes forces developers to rework plans to meet newer city code. The April conditions replaced that standard with a fixed restart date for the clubhouse.
The Construction Plan for Ute Avenue
Crossland Construction replaced PCL as general contractor this summer and filed a construction-management plan dated Aug. 3, 2026, along with a schedule of more than 2,300 milestones. The construction-management plan calls the schedule a "living document." Muhigirwa said it is used for planning, not as a binding commitment. Its targets are:
- Fall 2026: clubhouse foundation prep, rough plumbing, electrical and heating, plus structural checks and weatherproofing on the townhomes
- Later in 2027: possible start of the affordable housing, depending on progress at the clubhouse pool
- Second quarter of 2029: final inspections for the three townhome clusters
- Fourth quarter of 2029: final inspections for the 12 workforce housing units
- Third quarter of 2030: final inspection for the clubhouse
- Around January 2031: overall completion
The plan describes the street-level effects. Project traffic is routed along Main Street, Original Street and south on Ute Avenue. Construction vehicles are capped at 65,000 pounds, and deliveries are scheduled during normal work hours with no road closures. Work in the Ute Avenue right-of-way includes new asphalt, curb and gutter, drive approaches and storm inlets. It is to be sequenced so a single lane stays open, with signage and flaggers, and any disruption to the driveways of the two neighboring properties on the adjacent cul-de-sac is to be worked out directly with those neighbors. The plan states that snow removal, bus routes and public parking will not be affected. Separately, the 2010 approval ordinance bars any use of the Aspen Club Trail for construction activity.
The plan, filed with the city, covers a disturbance area of 2.36 acres between Ute Avenue and the Roaring Fork River. Crossland names superintendent Braden Scott as the project liaison and sole point of contact for public communication, and says it will post public updates at the site.
The Community Benefits in the Approvals
This part of the story gets the least attention and lasts the longest. The 2010 ordinance tied the timeshare entitlement to community obligations. Aspen Journalism reports that those conditions still apply after the 2015 plan modifications.
| Obligation under the approvals | What has to happen first |
|---|---|
| Memberships open to the general public | A completed, operating club |
| Free office space for two local charities | A completed clubhouse |
| Project Graduation, athlete training, public seminars and lectures, community gatherings | A completed clubhouse |
| 12 two-bedroom affordable units, available through the Aspen-Pitkin County Housing Authority | Final inspection, targeted for Q4 2029 |
| 0.25% assessment on each fractional sale for the Community Health and Recreation Fund | Closed timeshare sales |
The fund shows what ten years of delay cost. The assessment was set to run for 25 years from approval, which means it ends in 2035. Nothing has been collected yet. Under the current schedule, Aspen Journalism estimates the fund would receive about four years of collections out of a 25-year life. Each quarter the schedule slips takes more away from that window.
Reading the East End Through This Winter
For a buyer comparing the East End with the West End or Cemetery Lane, the Aspen Club is more than background. It shapes what the end of Ute Avenue will be like to live near for years. At its peak the club had more than 1,000 members and 200-plus employees. It offered tennis, Pilates, weightlifting, basketball, physical therapy, a pool and a spa, and it served as the neighborhood's social center. Since 2016 that space has been an unfinished site that Aspen Journalism, describing the view from the Ute Trail, called "a dirt-brown postage stamp surrounded by aspens and evergreens."
The construction plan includes a published route, a named liaison and a schedule running to early 2031. The architect described the planned club as a "modern performance center and wellness destination," with more space for dining, socializing and recovery relative to exercise.
If the clubhouse permit lapses, the city's own description of that outcome applies: a final act that can affect vested rights and send plans back to meet current code. Under that scenario, the 14 partially built townhomes, which show weathered siding and cracked stonework after years of exposure, sit beside a clubhouse with no valid permit. The city has said it is not concerned about the structures from a structural standpoint.
FAQ
Is the Aspen Club open for memberships this winter? No. The facility has stayed closed since 2016, and under Crossland's schedule the clubhouse's final inspection is targeted for the third quarter of 2030.
Who is building it? Crossland Construction has been general contractor of record since it replaced PCL in summer 2026. Oz Architecture has handled the redesign.
This post summarizes public reporting and city records on a single project. It is general information, not legal, tax or financial advice, so confirm how any permit, entitlement or ordinance applies to your property with the right professional.
At Lex Tarumianz Realty, we track entitlement deadlines like this one parcel by parcel, because a permit decision on Ute Avenue can change the value of homes several doors away. If you are weighing an East End purchase or sale around the Aspen Club's timeline, request a confidential consultation and we will walk through what the Dec. 31 outcome means for your specific property.